Pakistan energy and load shedding problem solution by biogas
water tank |
pvc pipe |
Add caption |
cut the top off 1500 l digester tank |
1500 l digester tank |
1500 l digester tank with hole |
outlet pipe at top of the tank |
heat iron pipe for making hole in tank |
make a 75 mm hole for inlet near the base of the tank on opposite side to the outlet |
hole in tank |
pvc pipe |
Put OUTLET pieces together like this and fit onto the DIGESTER tank |
For all threaded fittings, apply white thread tape to | improve the seal |
|
Add caption |
Apply EPOXY RESIN around ALL joints | touching the tanks to make water/gas |
75mm fittings for the INLET/FEEDPIPE |
Constructing a Floating Drum Biogas Digester inlet Part 3 |
biogas tank inlet volve |
Constructing a Floating Drum Biogas Digester inlet Part 3 |
Insert FEED PIPE 1.2 m long into TEE |
Make ½” (12.5mm)hole in the TOP of the gas holder tank. The hole should be near the EDGE of the tank |
13.5 mm gas fittings |
Fit the male adapter to the inside of gas holder tank |
Add caption |